Trump’s permitting crackdown strands U.S. wind and solar boom

Trump’s permitting crackdown strands U.S. wind and solar boom

Rule Changes

The Pentagon cleared two onshore wind projects, but the administration is reopening offshore permits and Democrats say the deal still isn't safe.

Overview

Updated Oct 29

The Pentagon has started clearing onshore wind projects again after a federal judge ordered it to resume reviews. In October it advanced projects in Maine and South Dakota, but Democrats say hundreds more are still waiting.

At the same time, the Justice Department is asking courts to reopen permits for four offshore wind farms, including New England Wind off Massachusetts. The Senate is due to take a first procedural vote on the bipartisan permitting bill on Nov. 9, and four Democrats want billions in canceled clean energy grants restored before then.

Why it matters

The fight decides whether wind and solar can power AI data centers or utilities lean harder on gas.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

1 vs 15
New large solar projects on federal land: Trump vs Biden
Only one major solar project was approved on federal land before an April 2026 court order forced Interior to resume reviews, compared with 15 under Biden.
500+
Solar and storage projects at risk nationwide
Industry groups say more than 500 projects could be delayed or derailed by the freeze.
92 GW
Clean energy capacity facing heightened federal scrutiny
A June 2026 Wood Mackenzie report found 92 gigawatts of wind, solar and storage projects, enough to power 69 million homes, still tangled in added federal review.
32%
Projected rise in U.S. electricity demand by 2030
Grid Strategies projects a 32% demand jump by 2030, over half from data centers.
28 days
Maximum timeline for fossil fuel and mining permits
Interior's emergency procedures cap fossil and mining permitting at 28 days, far faster than renewables.
33 GW
Nevada solar and storage pipeline tied up by federal delays
Nevada's governor says more than 33 gigawatts near federal lands face permitting uncertainty.
$121B
Wind and solar investment at risk from stalled permits
Wood Mackenzie estimates $121 billion in wind and solar investment is threatened by lingering federal permitting delays as of June 2026.
110
Wind projects still in Pentagon review limbo as of Sept. 30
The Justice Department told a court on Sept. 30 that 110 projects were mid-negotiation on airspace mitigation and had not been contacted since the August injunction. The Pentagon has since cleared at least two onshore projects.
Nov. 9
First Senate procedural vote on the permitting bill
Senate leaders expect the first procedural vote on the American Affordability and Jobs Act on Nov. 9, after the midterms.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

U.S. Department of the Interior
U.S. Department of the Interior
Federal Cabinet Department
Appealing the April injunction; the Justice Department is also asking courts to reopen four offshore wind permits.

Interior holds the keys to federal lands and many of the permits wind and solar projects rely on.

American Clean Power Association
American Clean Power Association
Trade association
Counting 17 federal actions restricting renewable development; courts have blocked several

ACP represents wind, solar, storage and transmission companies now watching federal permits stall.

Solar Energy Industries Association (SEIA)
Solar Energy Industries Association (SEIA)
Trade association
Coordinating solar sector response to the federal permitting freeze

SEIA is the main voice of the U.S. solar industry, now alarmed by stalled federal reviews.

U.S. Army Corps of Engineers
U.S. Army Corps of Engineers
Federal agency
Controls key water and wetlands permits affecting many renewables on private land

The Corps issues Clean Water Act permits that many solar and wind projects can’t build without.

U.S. Fish and Wildlife Service
U.S. Fish and Wildlife Service
Federal Agency
Tightening wildlife reviews, creating another bottleneck for wind and solar

Fish and Wildlife oversees endangered species reviews that many renewable projects must clear.

United States Department of Defense
United States Department of Defense
Federal agency
Began clearing some onshore wind projects in October after a court order; Democrats say hundreds remain in limbo.

The Pentagon reviews wind projects near military installations for radar and training interference, and its sign-off is often required alongside Interior's.

Timeline

January 2025 October 2026

27 events Latest: October 28th, 2026 · 2 weeks ago Showing 8 of 27
Tap a bar to jump to that date
  1. Senate Democrats tie permitting vote to restoring clean energy grants

    Latest Political

    Four Senate Democrats pressed the administration to restore billions in terminated Energy Department clean energy awards before the permitting bill reaches a vote.

  2. Wyoming approves $1.1 billion Laramie Range wind farm

    Regulatory

    The state Industrial Siting Council approved Repsol's Laramie Range Wind Project with 26 conditions after two days of public comment.

  3. White House advances two onshore wind projects

    Regulatory

    The administration moved Maine and South Dakota wind projects that had been held in a Pentagon review. Democrats called it a start but said hundreds more remain in limbo.

  4. Bipartisan permitting bill introduced in Senate

    Legislative

    Whitehouse, Capito, Heinrich and Lee introduced the American Affordability and Jobs Act, which would lock in permits for approved projects and make data centers pay for their transmission lines.

  5. Report: Pentagon delay is the key sticking point in permitting talks

    Analysis

    The American Clean Power Association counts 17 federal actions restricting renewable development, most still in force. Courts have blocked several, including the Pentagon's wind review freeze.

  6. Senate permitting bill pushed past midterms

    Political

    Roll Call reports the bipartisan permitting deal is close but won't move until after the November elections. Whitehouse says negotiators are "over the hump" on the deal-break issues.

  7. Senators demand Interior follow court order on renewables

    Political

    Hickenlooper, Bennet and Luján wrote to Burgum that developers still face illegal delays four months after the April injunction, saying Interior staff keep demanding paperwork the courts barred.

  8. Report finds $121 billion in wind and solar investment at risk

    Analysis

    Wood Mackenzie finds 92 gigawatts of clean energy projects, enough to power 69 million homes, still face heightened federal scrutiny.

  9. Burgum vows to appeal ruling, clashes with Congress over Nevada delays

    Political

    Testifying before the House Natural Resources Committee, Burgum says he will "absolutely" appeal the Casper injunction; Rep. Susie Lee says his policies "created a total permitting mess" in Nevada.

  10. Senate Democrats tie permitting reform to fair treatment of renewables

    Political

    Senators Martin Heinrich and Angus King tell Burgum they'll block bipartisan permitting reform unless Interior stops slow-walking wind and solar; Burgum tells Sen. Cortez Masto he's willing to process permits.

  11. Interior starts approving stalled solar permits, but wind stays frozen

    Regulatory

    After months of pressure, Interior begins moving some solar permits again, but onshore wind projects on federal land remain stuck.

  12. Trump administration holds major Gulf of Mexico oil and gas auction

    Policy

    Interior offers over 80 million offshore acres at reduced royalties, underscoring fossil fuel priority.

  13. Analysts project data center power demand will double by 2030

    Analysis

    Gartner warns data centers’ electricity use will double by 2030, heavily driven by AI.

  14. Nevada governor warns 33 GW of projects face federal delays

    Political

    Governor Joe Lombardo tells Burgum that federal holdups threaten Nevada’s power supply and data center plans.

  15. Army Corps and Fish and Wildlife tighten renewable project reviews

    Regulatory

    Agencies prioritize high energy‑density projects and restrict automated tools for wind and solar developers.

  16. Interior questions whether wind and solar belong on federal lands

    Policy

    Burgum’s order says massive wind and solar may unduly degrade lands compared with denser energy sources.

  17. Burgum memo requires personal sign-off on every renewable decision

    Regulatory

    An internal memo mandates Burgum personally approve all wind and solar decisions, cradle to grave.

  18. Interior adds extra layers of review for wind and solar

    Regulatory

    Interior orders elevated Secretary’s Office review for virtually all actions involving wind and solar facilities.

  19. Interior invokes emergency powers, caps many fossil permits at 28 days

    Policy

    Interior implements emergency procedures slashing multi‑year energy permitting processes down to 28 days.

  20. Army Corps quietly pauses 168 renewable-related permits

    Regulatory

    Army Corps temporarily halts evaluations of 168 renewable permits, citing Trump’s new energy agenda.

  21. Doug Burgum installed as Interior Secretary, launches energy dominance orders

    Policy

    Burgum signs initial secretarial orders to unleash American energy and streamline fossil permitting.

  22. Trump takes office and orders halt on new federal wind approvals

    Policy

    On inauguration day, Trump directs agencies to pause new wind permits and reorient energy policy.

Scenarios

1

Courts Chip Away at Trump Freeze, Forcing Interior to Restart Renewable Permitting

Possible

Discussed by: Reuters, legal analysts, environmental groups watching the December wind ruling

Judge Saris’ decision striking down the wind moratorium becomes a template for broader lawsuits targeting Burgum’s personal sign‑off rule and Interior’s de facto moratorium on solar. States, trade groups and NGOs file Administrative Procedure Act challenges arguing the policies are arbitrary and conflict with statutory mandates to develop renewables. Courts don’t rewrite energy policy overnight, but a series of rulings forces Interior to issue clear criteria and resume processing at least some wind and solar permits.

2

Freeze Holds Through Trump’s Term, Data Centers and Utilities Scramble for Alternatives

Likely

Discussed by: Industry executives quoted by Reuters, Grid Strategies and other power-market analysts

Legal challenges drag on while Interior keeps its hands on the spigot. Burgum’s office continues slow‑walking or shelving federal-land projects, and other agencies maintain stricter reviews that make even private-land renewables harder. Utilities sign more gas contracts and extend aging fossil plants to feed data centers, while tech companies quietly bankroll bespoke nuclear, gas peakers and overseas renewables. The U.S. meets most new demand, but with higher emissions, higher volatility and deeper regional reliability worries.

3

Backlash Spurs Bipartisan Deal to Fast-Track Clean Power for AI and the Grid

Uncertain

Discussed by: Some utility planners, Wall Street analysts, and pro-business Republicans alarmed by supply risks

As grid planners warn of capacity shortfalls and high prices, pressure builds from governors, tech giants and industrial users who need predictable power. Congress hammers out a narrow deal: keep Trump’s 28‑day timelines and some energy‑density language, but extend similar fast‑track treatment to large transmission lines, storage and certain utility‑scale renewables tied to data centers and manufacturing. Interior retains ideological skepticism of wind and solar, yet is forced to clear defined project classes, partially thawing the freeze.

4

1st Circuit Rules on Interior's Appeal of the Wind and Solar Injunction

Uncertain Resolves by Q2 2027

Discussed by: Law firms tracking the case, including McGuireWoods and Crowell & Moring

Interior has appealed Judge Casper's April 2026 injunction to the 1st U.S. Circuit Court of Appeals. A ruling upholding the injunction would lock in faster permitting nationwide; a reversal would let Interior reinstate its sign-off rule and added reviews.

5

Wind Permitting on Federal Land Stays Frozen Even as Solar Resumes

Likely Resolves by End of 2026

Discussed by: E&E News reporting, Sandra Purohit of business group E2

Despite the Casper injunction covering both wind and solar, Interior has resumed some solar approvals while onshore wind projects on federal land remain stalled. E2's Sandra Purohit says there hasn't been enough movement to affect prices.

6

American Affordability and Jobs Act Clears Congress After Midterms

Possible Resolves by End of 2026

Discussed by: Roll Call, PBS News, Senate negotiators

The bipartisan bill would lock in permits for already-approved energy projects and make data centers pay for their own transmission lines, limiting how much the White House can reverse approvals. Democrats say they'll only trust it if the administration lets wind and solar actually proceed.

7

Offshore Permit Reversals Sink the Senate Permitting Deal

Deadline passed (Nov 9, 2026)

Discussed by: Sen. Sheldon Whitehouse; Politico

The Justice Department's requests to reopen four offshore wind permits give Democrats a reason to walk away. Whitehouse says the renewed attacks could 'blow up' the bipartisan bill, and the first procedural vote is expected Nov. 9.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

2021–2022

Biden’s Oil and Gas Leasing Pause on Federal Lands

Early in his first term, President Biden paused new oil and gas leasing on federal lands while agencies reviewed climate impacts and royalty terms. Republican states sued, arguing the pause violated federal leasing laws and administrative procedure requirements.

Then

Federal courts forced the administration to resume leasing while it rewrote rules and environmental reviews.

Now

Biden shifted from blanket pauses to more targeted restrictions and higher royalties, showing courts can constrain sweeping energy moratoria.

Why this matters now

It illustrates how aggressive, ideologically driven energy shifts—whether pro- or anti-fossil—can be checked by courts insisting on reasoned, lawful rulemaking.

2018–2022

Trump’s First-Term Tariffs on Imported Solar Panels

In 2018, Trump imposed safeguard tariffs on imported solar modules to protect domestic manufacturers. The move raised project costs and chilled some utility-scale solar investments, especially early in the tariff period.

Then

Installations dipped and some projects were delayed or resized as developers reworked budgets and supply chains.

Now

Costs kept falling, developers adapted, and solar growth resumed, but the episode showed how quickly policy shocks can slow deployment.

Why this matters now

It foreshadows today’s permitting freeze: different tool, same effect of injecting sudden policy risk into long-horizon renewable investments.

2015–2023

UK’s De Facto Ban on Onshore Wind in England

Planning rule changes in 2015 made it extremely difficult to build new onshore wind farms in England, even without an explicit legal ban. Local objections and complicated approval hurdles effectively froze development while offshore wind boomed.

Then

Onshore wind construction collapsed, and the UK leaned more heavily on gas and offshore projects.

Now

Energy-price and climate pressures pushed the government to relax rules and restart onshore projects in the 2020s.

Why this matters now

It shows how procedural and permitting tweaks can function as a stealth moratorium—and how political pressure can eventually force a rethink.