Finland orders Google to halt data center work after forest clearing
Built World
Finnish police have opened a criminal investigation into Google's Tuike Finland over suspected water-law breaches at the Muhos data center site, a case expected to run into 2027.
Finnish police have opened a criminal investigation into Google's subsidiary Tuike Finland over suspected breaches of the country's Water Act at the Muhos data center site. Officers are examining drainage and water management at the site, where about 330 hectares of forest were cleared before the required environmental review was finished. A guilty finding could lead to a corporate fine.
Google says it will cooperate with the investigation and focus on keeping its sites compliant. The regulator, LVV, had given the company until November 5 to submit a detailed water-management plan. Police plan an update in December and expect the investigation to run into 2027.
Why it matters
A criminal probe into water-law breaches will test whether Finland can enforce its environmental rules against Europe's largest AI build-out.
Questions about this story
Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.
No questions yet — be the first to ask.
Key Indicators
330
Hectares of forest felled at Muhos
Reported by Tuike Finland to the LVV as felled or prepared at the Muhos site.
200
Hectares prepared at Kajaani-Otanmäki
Area reported cleared or prepared at the second site, just under 200 hectares.
€13B
Google's planned investment in Finland
Announced September 2026 as the company's biggest single investment in Europe, with a third site planned in Vaala.
1,400
Hectares of forest sold to Google
Metsähallitus, the state forest enterprise, sold the mostly commercial forest at Muhos and Kajaani for over €27 million.
Nov 5
Deadline for Google's water-management plan
The deadline has passed. LVV had said a conditional fine was possible if Google did not act.
2027
Expected end of police investigation
Police say they will give an update in December and expect the criminal investigation to run into 2027.
24 events
Latest: October 29th, 2026 · 1 week ago
Showing 8 of 24
JK to step
Tap a bar to jump to that date
Jump to
October 2026
Police open criminal investigation into Muhos site
LatestInvestigation
Finnish police said they were investigating whether Tuike Finland breached the Water Act and caused environmental damage at the Muhos site. A guilty finding could lead to a corporate fine, and police said the inquiry would run into 2027.
Stora Enso admits taking timber from Google sites
Disclosure
Stora Enso says its Oulu unit received about 5,000 cubic metres of log and pulp wood from the disputed Muhos felling, after earlier denying any link. UPM and Metsä Group had already suspended deliveries of small volumes received through contractors.
Suspension deadline
Compliance Deadline
Latest date by which suspension of major site work must be in effect at both locations.
Regulator refers Muhos site to police
Investigation
LVV files a criminal complaint (tutkintapyyntö) over the Muhos site, saying roughly five miles of drainage ditches were dug without the required advance notification. Police say no preliminary assessment has started and they are waiting for the regulator's statement.
LVV sets November 5 water-plan deadline
Regulatory Decision
LVV gives Google until November 5 to submit structures, their locations, a construction timetable and independent water monitoring. It says drainage may need a permit under the Water Act because black shale deposits could raise acidity and metal levels, and raises the prospect of a conditional fine.
Guardian details scale of Muhos clearing
Investigation Report
The Guardian reports an estimated 250,000 trees cleared from 330 hectares at Muhos, with wolves driven into the nearby town and locals describing the site as a wasteland. It dates Google's halt order to early October.
Tuike response deadline
Compliance Deadline
Tuike Finland submitted its written response on October 11, before the deadline, confirming work had stopped and requesting written pre-approval for any necessary stabilisation work.
Muhos building inspector granted leave
Personnel
Muhos's leading building inspector Jultuz Änwär was granted leave of absence, Helsingin Sanomat reported, as questions mounted about how the clearing proceeded with municipal approval.
Google Finland chief apologises
Statement
Antti Järvinen apologised for the forest clearances at Muhos and Kajaani, saying Google had acted to the best of its understanding of the law and had not rushed the work ahead of environmental assessment.
Google submits response to LVV
Compliance
Tuike Finland submitted its written response to the LVV, confirming work had stopped and saying it would seek written pre-approval for any necessary stabilisation work. Google said it would complete the environmental assessments within six weeks for Kajaani and ten weeks for Muhos.
Minister says no sanction for clearing under current law
Government
Environment and Climate Minister Sari Multala said current environmental impact assessment law does not directly allow sanctions for the clearings. Parliament is considering legislation to tighten environmental licensing penalties.
LVV orders halt to major site work
Regulatory Decision
Regulator orders Tuike to stop felling, digging and quarrying; The Guardian reports the story same day.
Private complaint filed over Muhos clearing
Investigation
A private individual asks police to investigate preparatory work at Muhos. As of late October, police said no preliminary assessment had begun on that request or on the regulator's separate referral.
September 2026
Tuike says no permit was needed
Legal Argument
In its LVV reply, Tuike argues its preparatory work required no permit, citing Muhos guidance.
LVV requests information
Investigation
Regulator seeks details from Tuike, Muhos municipality, Kajaani city and building-control authorities.
August 2026
Logging continues despite ruling
Violation Allegation
Satellite data shows clearing continued until August, after the LVV's May decision.
June 2026
Muhos building control says section 109 works are possible
Permitting
Despite the LVV's May 18 warning, Muhos building control determines that the section 109 groundwork can proceed. Declic Media notes the EIA law governs when, not whether, such works are authorized.
May 2026
Regulator rules EIA is mandatory
Regulatory Decision
LVV says the projects fall directly under the EIA requirement in item 2(f) of the law.
LVV warns Muhos no permit may precede EIA conclusion
Regulatory Decision
The LVV tells Muhos building control that no permit for the works should be granted before the environmental impact assessment concludes.
Kajaani building permit application cites groundwork plan
Permitting
Tuike's building permit application for the Kajaani-Otanmäki site discloses preparatory works under section 109 of the Land Use and Building Act.
April 2026
Tuike asks whether review is needed
Compliance Question
Tuike Finland asks the LVV whether an environmental impact assessment is required for the sites.
March 2026
Tuike applies to Muhos for earthworks permit
Permitting
Tuike Finland files for a maisematyölupa (landscape work permit) with Muhos municipality, before the EIA is complete.
Clearing begins at Muhos
Construction
Logging and topsoil removal start at the planned Muhos data center site.
2024
State forest sale to Google
Transaction
Metsähallitus sells 1,400 hectares of forest at Muhos and Kajaani for over €27 million.
Scenarios
1
Google complies, projects proceed after review
Likely
Resolves by End of 2026
Discussed by: Yle, TechTarget; the LVV framed its order as a temporary, limited halt
Tuike Finland complies by the October 23 deadline, limited work such as planning and soil surveys continues, and the environmental impact assessments conclude in late 2026. The LVV lifts the suspension for one or both sites, and construction proceeds, possibly with conditions such as the 130 hectares of tree planting Google already proposed at Muhos.
2
LVV imposes fines for non-compliance
Possible
Resolves by Jan 31, 2027
Discussed by: TechTarget; LVV said it would seek formal enforcement backed by a conditional fine
Tuike Finland fails to stop major site work by October 23. The LVV moves from voluntary compliance to a formal enforcement procedure, likely imposing a conditional fine that escalates until the work stops. This would test whether Google absorbs the cost or halts voluntarily.
3
Police bring charges over Muhos clearing
Possible
Resolves by Q2 2027
Discussed by: Yle and Iltalehti reporting on the preliminary investigation
The preliminary inquiry opened on October 2 finds sufficient evidence of a crime in the preparatory work at Muhos, and public prosecutors open a pre-trial investigation or file charges. A conviction could carry fines or other penalties, separate from the LVV's administrative action.
4
Google cancels or relocates one or both sites
Unlikely
Resolves by End of 2027
Discussed by: Futurism and TechSpot coverage raising project-risk questions
The environmental review or the legal fallout makes one or both sites untenable, and Google abandons or moves the projects. The LVV's order does not cancel either project, and Google's 13 billion euro commitment argues against a retreat, but a worst-case EIA outcome or sustained legal pressure could change the calculus.
5
Sites stay idle into spring as EIA runs long
Possible
Resolves by Q1 2027
Discussed by: Lapin Kansa
The LVV holds to its requirement that the environmental impact assessment be complete before work resumes. Google's own estimate is six weeks for Kajaani and ten weeks for Muhos, but if the assessment runs longer or the LVV demands more, the sites could stay idle into spring. Google has said it may need to do stabilisation work in the meantime, with written pre-approval.
Historical Context
2 moments from history that rhyme with this story — and how they unfolded.
1 of 2
2024-2025
Google Chile data center water ruling (2024)
Chilean courts ordered Google to suspend operations at its data center in drought-prone Santiago over its water use. The company drew water under permits that authorities and courts found did not match actual consumption during a severe drought.
Then
Google suspended or scaled the facility's water use and appealed; the case became a flashpoint in Chile's water politics.
Now
It established that data center infrastructure in resource-stressed regions can face court-enforced environmental limits.
Why this matters now
Like the Finnish case, it shows Google's data center build-out colliding with local environmental regulation, where a government body halts operations over compliance.
2 of 2
2022-2028
Ireland data center grid moratorium (2022)
Ireland's grid operator, EirGrid, paused new data center connections in Dublin until 2028 because data centers consumed nearly a fifth of national electricity, straining the grid.
Then
New data center connections in Dublin were refused; developers shifted to other Irish regions.
Now
The moratorium set a European precedent for regulators limiting data center growth on infrastructure and environmental grounds.
Why this matters now
It parallels how Finland's regulator is using its own permitting system to control where and how data centers are built, tying big tech expansion to local capacity and environmental review.