Says the transmission gap should narrow within about 18 months and battery storage has reached nearly 10 GWh; opposing CERC's proposed deviation penalties
India's grid could not absorb 6,825 gigawatt-hours of renewable power in the first half of 2026, 4.9% of renewable generation and 1.8 times the whole of 2025, per Aurora Energy Research. September's curtailment fell to 378.52 million units, 1.28% of renewable output, which JMK Research called seasonal relief rather than a fix.
Updated Oct 30
Tracks renewable deployment and reports curtailment data
India's grid can't move the renewable power it generates. About 21 GW of clean energy runs on temporary connections, and 12 GW gets cut off during peak solar hours.
Updated Oct 23