Pull to refresh
Logo
China installs world's largest offshore converter station off Guangdong

China installs world's largest offshore converter station off Guangdong

New Capabilities

Power now flowing: five Qingzhou turbines feed China's 25,000-tonne 'Heart of the Sea Wind' station, which sends their output ashore as ±500 kV DC

Overview

Updated Oct 24

Power is flowing from the world's largest offshore converter station, roughly 100 kilometers off Guangdong's coast. On September 27, the first five turbines at the Qingzhou V and VII wind farms began sending electricity through the 25,000-tonne Heart of the Sea Wind station, which converts it to ±500-kilovolt direct current for the trip ashore.

The station gathers power from 163 turbines, raises the voltage and converts it to direct current, which loses far less energy than alternating current over long submarine cables. At full output the project is expected to send about 6 billion kilowatt-hours a year to the Guangdong-Hong Kong-Macao Greater Bay Area. That works out to nearly 5 million tonnes of carbon dioxide avoided annually, according to China Three Gorges Corporation.

Why it matters

Deep-sea wind power now reaches Guangdong without losing most of its energy — up to 6 billion kWh a year along that line.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

25,000 tonnes
Weight of converter station
The upper structure alone weighs 25,000 tonnes, requiring a float-over installation because no domestic crane could lift it.
2,000 MW
Transmission capacity
First ±500 kV, 2,000 MW flexible DC offshore converter station in the world.
6 billion kWh/year
Annual power delivery at full output
Clean electricity expected to reach the Guangdong-Hong Kong-Macao grid each year once all turbines are online.
1,090 nautical miles
Sea voyage from Nantong to Yangjiang
The station was carried on a semi-submersible vessel from Jiangsu province to its final site.
90 km
Farthest distance offshore
The Qingzhou V and VII site sits up to 90 kilometers from land, in water as deep as 53 meters.
163
Wind turbines served
The station collects power from turbines across the Yangjiang Qingzhou V and VII offshore wind farms.
5
Turbines connected to the grid
China Three Gorges connected the first five Qingzhou turbines on September 27, 2026.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

May 2026 October 2026

7 events Latest: October 12th, 2026 · 1 month ago
Tap a bar to jump to that date
  1. Energy China details the project's world-first list

    Latest Disclosure

    EPC contractor Energy China GEDI described the scheme as a ±500 kV/2,000 MW flexible DC link with 66 kV collection cables and the first application of ±500 kV DC submarine cable.

  2. Station settled in place off Yangjiang, commissioning continues

    Milestone

    State media confirmed the structure is fully positioned in the Qingzhou sea area; it will deliver about 6 billion kWh of green power yearly once operational.

  3. First five turbines connect to the grid

    Milestone

    China Three Gorges connected the first five Qingzhou V and VII turbines to the grid through the Heart of the Sea Wind station. At full capacity the project is expected to deliver about 6 billion kWh a year to the Greater Bay Area.

  4. Station moves to final cabling and testing phase

    Milestone

    Reports confirmed the station fully installed about 100 km offshore; subsea cable installation and joint offshore-onshore testing began before commercial operation.

  5. Full offshore installation declared complete

    Verification

    China Classification Society confirmed the leg mating unit welding finished, completing all offshore structural work.

  6. Float-over installation completes with millimeter precision

    Installation

    After seven hours of positioning, the station's eight insertion spikes locked into the seabed jacket foundation off Yangjiang, setting six world records.

  7. Heart of the Sea Wind departs Nantong

    Logistics

    The 25,000-tonne converter station left Nantong, Jiangsu province, on a semi-submersible vessel for a 1,090-nautical-mile voyage to Yangjiang.

Scenarios

1

Heart of the Sea Wind begins commercial operation by mid-2027

Likely Resolves by Q2 2027

Discussed by: CGTN, SASAC, and project disclosures describing the commissioning path

Subsea cables get laid without major setbacks, joint offshore-onshore testing passes, and the station begins feeding the Guangdong grid. China Three Gorges announces grid connection and the first delivered power.

2

Model replicated: China orders comparable stations for future deep-sea projects

Possible Resolves by Q2 2028

Discussed by: China Electricity Council officials and state media framing the project as a template

Once the technology proves out, Chinese developers order similar ±500 kV flexible DC stations for other far-offshore wind bases, scaling the 10 GW-class Yangjiang build-out and similar projects in the East China Sea.

3

Commissioning slips into 2028 on cable or integration problems

Unlikely Resolves by Jan 31, 2028

Discussed by: The complexity of the first ±500 kV DC submarine cable plus joint offshore-onshore testing

Faults emerge in the world's first ±500 kV submarine DC cable or in grid synchronization, pushing first commercial power past initial schedules. Station remains installed but idle beyond early 2028.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

March 1954

Gotland HVDC Link (1954)

Sweden commissioned the world's first commercial high-voltage direct current (HVDC) link, a 20 MW, 98-kilometer submarine cable connecting the island of Gotland to the mainland. It was built mainly to transmit surplus wind power from the island.

Then

Gotland's wind power became sellable to the mainland, and the technology proved HVDC could cross open water efficiently.

Now

HVDC became the standard for long-distance and submarine power transmission worldwide, with voltages and capacities rising steadily over seven decades.

Why this matters now

The Heart of the Sea Wind is the direct descendant of this first link — same physics, same purpose, but 100 times the voltage and carrying far more power from dozens of turbines.

2009–2012

BorWin1 — First Offshore Wind HVDC Converter (2012)

Germany's BorWin alpha went into service in the North Sea as the world's first offshore wind HVDC converter station, collecting power from the 400 MW BorWin1 and BorWin2 wind farms and transmitting it to the mainland grid.

Then

It proved offshore conversion was technically feasible, opening the North Sea's deeper wind zones to development.

Now

Set the template China has now scaled: collect AC from turbines, convert offshore to DC, and ship it ashore with minimal loss.

Why this matters now

China used the same architecture but built it five times larger — 2,000 MW at ±500 kV versus BorWin's 400 MW — and made all key components domestically.

Sources

(13)