Opposing the city takeover
PG&E told state regulators that a San Francisco takeover of its electric grid would cost $22.5 billion. Its Oct. 20 filing values the city assets at $13.9 billion and adds $8.6 billion in damages from cutting San Francisco's system away from the rest of the utility's network.
Updated Oct 21
As of May 2026: Leading operational response and investigation coordination during outage
San Francisco is the kind of city that feels unstoppable—until the lights go out. On Saturday, a substation fire near 8th and Mission helped trigger a blackout that spread across neighborhoods and knocked out traffic signals. Restoration took more than two days and sparked political backlash and raised questions about whether a modern city can tolerate single-point failures in critical infrastructure.