Transmission network owner
Appears in 2 stories · Last updated Nov 4, 2026
Owns the South Australian section
At 12:30 pm on 4 November 2026, the Australian Energy Market Operator put three 330-kilovolt lines into service in western New South Wales. The Bunday–Buronga line and the two Buronga–Dinawan lines are the second circuit of Project EnergyConnect, the 900-kilometre link between South Australia and New South Wales. Their commissioning started the inter-network testing program that governs how fast the link's capacity grows.
Updated 7 days ago
As of September 2026: Completed its section of Project Energy Connect on time and on budget
Transgrid's plan would have added about A$18 to the average household power bill in 2027-28 to cover overruns on Project Energy Connect. Australia's energy regulator said no on September 1, provisionally rejecting the A$1.2 billion recovery bid.
Updated Sep 2